The Project Online retirement took effect on September 30, 2026, and many organizations are now evaluating replacement platforms, rebuilding reporting, and determining how to manage historical project data. Project Web App (PWA) is no longer available, Power BI dashboards connected to Project Online have stopped refreshing, and project managers are asking where their project data went. Whether your team planned ahead or is scrambling now, this migration guide walks you through seven practical steps to protect your data, choose the right replacement, and get your project portfolio management (PPM) back on track.
Key Takeaways
Project Online retired on September 30, 2026. Microsoft Project desktop, Project Server, and Microsoft Planner still work.
Secure any remaining project data first, then assess your needs before picking a platform.
The main replacements are Project Server Subscription Edition, Planner Premium, and Dynamics 365 Project Operations.
Plan to rebuild Power BI reports, custom fields, and workflows. Migration tools won’t handle everything.
What the Project Online Retirement Means for Your Organization
Microsoft stopped selling Project Online-only plans in October 2025 and has now fully shut the service down. For organizations that ran their PPM on Project Online, that means losing access to PWA, the OData reporting feed, custom fields, workflows, and the enterprise resource pool that tied everything together. Some of that loss came early. Microsoft retired the SharePoint 2013 workflow engine in Microsoft 365 on April 2, 2026, so many Project Online workflows, such as approval flows, stage-gate automation, and status updates, stopped running months before the final retirement date.
The good news is that the Project Online end of life doesn’t have to derail your projects. With a clear plan, most organizations can recover, migrate, and even come out with a more modern setup. Here’s where to start.
Confirm What Actually Shut Down
Not everything with “Project” in the name is gone. The retirement applies only to Project Online. Microsoft Project desktop, Project Server, and Microsoft Planner are not affected. Teams using Microsoft Project desktop with local MPP files can keep working as usual.
It also helps to clear up another common mix-up. Project for the web was retired separately in 2025, and its features were folded into Microsoft Planner.
Share a short, clear message with your users early. It will save your help desk from a flood of tickets and prevent unnecessary panic.
Secure Your Project Data
Next, take inventory of what was exported before the shutdown. Check with each PMO lead and project manager whether they saved:
Project plans (MPP files)
Timesheets and actuals
Custom fields and lookup tables
Resource assignments and resource allocation data
Issues, risks, and change requests
Historical project data needed for audits or compliance
Exports are often handled by individual teams rather than centrally, so gaps are common. Gather everything in one secure location with clear ownership.
Assess What Your Organization Really Needs
Before choosing a new platform, step back and look at how your organization actually used Project Online. Many teams paid for enterprise features they rarely touched, while others relied heavily on capabilities that not every replacement offers.
Ask questions like these:
Resource management: Do you need enterprise-wide resource planning and capacity planning, or just task assignments within teams?
Portfolio governance: Do you use demand management, project requests, scenario planning, or portfolio balancing to prioritize work?
Reporting: Which portfolio dashboards and reports does leadership actually rely on? Do you track outcomes through benefits realisation tracking?
Risk and issue tracking: Do your teams use RAID management (risks, assumptions, issues, and dependencies) to keep projects on track?
Financial tracking: Do you track budgets, costs, or billing inside your PPM tool?
Compliance: Do you have data residency, enterprise security, role-based security, or audit history requirements?
Integration: How important is Microsoft 365 integration with Teams, SharePoint, and Power Platform?
Your answers will point you toward the right platform and help you avoid choosing one you’ll outgrow.
Talk to Rob and our Project team for a quick assessment of your options.
We’ll help you match your actual PPM needs against Project Server Subscription Edition, Planner Premium, and Dynamics 365 Project Operations.
Choose the Right Replacement Platform
There’s no single successor to Project Online. Most former Project Online customers evaluate one of three Microsoft-focused options.
Project Server Subscription Edition is the closest Microsoft platform to the traditional Project Online/PWA experience. It keeps the familiar PWA interface, advanced scheduling, demand management, and project requests, all running on your own infrastructure. It’s a strong fit for organizations with strict enterprise security, compliance, or data residency requirements. Your project data stays in an enterprise database you control.
Microsoft Planner with premium capabilities (Planner Premium) is the cloud-first option. It offers timelines, dependencies, portfolios, goals, and Copilot-driven capabilities (depending on licensing), with strong Microsoft 365 integration and Microsoft Teams access. It works well for teams that want simpler, real-time project management and collaboration, though organizations used to advanced resource capacity planning or portfolio dashboards may need Power Platform extensions to fill the gaps.
Dynamics 365 Project Operations suits organizations that need financial management, resource management, and billing in one system, such as professional services firms.
For software development teams, Azure DevOps may also be worth considering alongside your main PPM platform.
| Project Server Subscription Edition | Planner Premium | Dynamics 365 Project Operations | |
| Deployment | On-premises | Cloud | Cloud |
| Best for | Complex PPM, strict compliance | Simpler work management | Project financials and billing |
| Feels closest to Project Online | Yes, PWA interface | Partly | No |
| Resource management | Advanced | Basic, extendable with Power Platform | Advanced |
| Microsoft 365 and Teams integration | Moderate (with additional configuration) | Strong | Moderate |
Pick Your Migration Approach
There are three common ways to approach a Project Online migration:
Lift and shift: Move existing projects and structure as-is to a new platform. It’s faster, but it carries over legacy architecture and old problems.
Greenfield deployment: Start fresh with a clean configuration and bring over only active projects. It takes more planning but results in a cleaner system.
Hybrid approach: Migrate active projects, archive historical project data, and redesign workflows gradually.
If you’re moving to Project Server Subscription Edition, plan how you’ll structure the Content DB (content database) for your project sites and data from the start, since it’s much harder to change later.
Whichever approach you choose, set realistic expectations for migration tools. They can move content quickly, but custom fields, workflows, enterprise calendars, and reporting usually need to be rebuilt or reconfigured by hand. Power Automate can replace many legacy PWA workflows, but they need to be redesigned, not copied.
Rebuild Your Power BI Reporting
Power BI reports built on the Project Online OData feed stop working once the data source is gone. Executives usually notice this first, since portfolio reporting and dashboards are often how leadership tracks progress.
Identify the reports that matter most, such as portfolio status, resource capacity, and financial tracking, and rebuild those against your new platform first. This is also a good time to retire reports nobody uses and simplify the ones that remain.
Check what Power BI reporting integration your new platform supports before rebuilding, since data sources and connectors differ between options.
Clean Up Connected SharePoint Sites
Many Project Online deployments included connected SharePoint project sites holding documents, risk management logs, issues lists, and deliverables. That content doesn’t disappear on its own, but it may no longer be linked to the projects it supported.
Audit these SharePoint sites, decide what to keep, and archive what’s no longer needed. Good governance here also matters for AI tools. Microsoft Copilot can surface old content that users can still access, so leftover project sites with loose permissions can become a risk. For more on this, see our guide to Microsoft 365 security issues we find before every Copilot deployment.
Frequently Asked Questions
Is Microsoft Project desktop being retired too?
No. Only Project Online was retired. Microsoft Project desktop, Project Server Subscription Edition, and Microsoft Planner are still available.
Can I still access my Project Online data?
After the retirement date, Project Online and its data are no longer accessible through the service. If you didn’t export your data, contact Microsoft support as soon as possible.
What replaced Project for the web?
Project for the web was retired in 2025, and its features moved into Microsoft Planner.
Can I move from Project Online to Project Server?
Yes. Project Server Subscription Edition is the closest option to Project Online, but custom fields, workflows, and reports usually need to be reconfigured.
How long does a Project Online migration take?
It depends on the number of projects, custom fields, workflows, and reports involved. An assessment is the best way to get a realistic timeline.
Moving Forward After the Project Online Retirement
The Project Online retirement is disruptive, but it’s also a chance to rethink how your organization manages projects, resources, and portfolios. Confirm what still works, secure your project data, assess what you really need, and choose a platform that fits how your teams actually work.
Windows Management Experts helps organizations plan, migrate, and support Microsoft Project and SharePoint environments. If you’re not sure where your data stands or which platform is right for you, schedule a consultation with our team and we’ll help you map out your next steps.
Not sure where your data stands or which platform is right for you?
Schedule a consultation with our Microsoft Project and SharePoint specialists and we’ll help you map out your next steps.